Next Steps at Stonehenge

Key milestones from now to 2014:

May/June 2012: Removal of Airman’s Cross memorial for safe storage during construction works. Construction begins at Airman’s Corner

July/Aug 2012: Stonehenge to welcome visitors during the Olympics as normal at the current facilities

Sept 2012: Improvement works to Longbarrow Roundabout begin

March 2013: A344 closed to traffic between the A303 and Byway 12 (access to current visitor facilities and car park via A360/ Airman’s Corner)

Summer 2013: Installation of Airman’s Cross memorial in visitor building precincts

Oct 2013: New visitor centre opens, existing facilities and car park decommissioned, fencing removed

From Autumn 2013: Re-landscaping work at the site of current facilities and car par

Summer 2014: Environmental improvement works completed

It is our intention to keep local residents, community groups and businesses fully informed about the project, and we will be sending out regular newsletters updating you on progress.